Project Info

Client:
Ministry of Water & Irrigation Morganti Group Inc.

Total Project Value:
14 Million USD

Project duration:
2004-2005

Project Description

The strategic purpose of the Ain Ghazal Pretreatment Plant (AGTP) project is to provide a steady flow at the outlet of the existing operation, maximize the use of the new 1500 mm diameter. pipes, optimize the use of the old 1200 mm siphon and minimize the overflow to WADI (environmental concern).
The proposed extension and modification of the AGTP included the following:

  • New rock trapping chamber and valve chamber.
  • New screening and distribution chamber.
  • New grit removal and modification of the existing grit removal plant.
  • Modification and renovation of the existing aeration tanks.
  • Modification and renovation of the existing blower building.
  • New box culverts 3 m x 3 m x 270 m.r.
  • New DN 1400 pipes 100 m.r.